Phase 1 Information for 4FRI
Phase 1 Statistics
- 724,000-acre treatment area
- Treatments located on the Kaibab, Coconino, and Tonto national forests
Phase 1 Timeline
- January 2011 — USFS issued its Proposed Action and Notice of Intent to complete an Environmental Impact Statement (EIS)
- February 2011 – USFS hosts Public Scoping Workshops
- June 2011 — USFS to award contract for thinning operations
- October 2011— USFS to publish Draft EIS
- April 2012 — USFS to sign Record of Decision